Bangladesh achieved a major milestone in its energy sector on Tuesday as the first unit of the Rooppur Nuclear Power Plant supplied 350 megawatts (MW) of electricity to the national grid on an experimental basis.
Under an agreement with the Russian contractor, the unit will undergo a 10-month trial run before beginning commercial electricity production at full capacity.
The Rooppur plant has two units, each with a generation capacity of 1,200 MW, giving the facility a total planned capacity of 2,400 MW.
The project is being implemented by the Bangladesh Atomic Energy Commission under the Ministry of Science and Technology.
The development marks an important step in Bangladesh’s efforts to expand its electricity generation capacity through nuclear energy.